The IFF-OBA team in collaboration with National Water Fund and ATAWAS organised the workshop “Go with the flow! Cash flow projections and project proposals” from 05.03.2024 to 07.03.2024 at the Maji House in Mwanza region. A total of 50 participants from 13 different WSSAs, representatives from commercial banks, EWURA, Ministry of Finance and the Ministry of Water were amongst the audience.
The objectives of the workshop were for water utilities to
The IFF Consultant conducted an interim visit from 14th – 15th November 2023. The aim of the visit was to assess the documentation of financial expenditure, to clarify some inconsistencies that occurred in the interim report. The team visited the constructed four (4) chamber intakes and one (1) collection chamber at Karanga river, installed pump with capacity 160m3/h at 26m Head and transformer, constructed control room and 2.3km transmission pipeline constructed.”
The IFF Consultant conducted an interim visit from 17th – 20th July 2023. The aim of the visit was to assess the documentation of financial expenditure, to clarify some inconsistencies that occurred in the interim report and to assess works progress on site. The team visited one of the eight boreholes, a pump procured under IFF OBA (250m3/hr capacity), the Mangamba treatment plant with the new rapid sand filter and the airport tank under construction (500 m3/hr capacity). The IFF Consultant also visited newly connected customers (domestic and kiosk) in Naliendele area and watched pipes excavation and fitting in Mbae Chundi area.
The IFF OBA team, in cooperation with the representative from the Ministry of Finance and Planning (MOFP), carried out a project verification visit to the Tanga UWASA on 21.06.2023-22.06.2023
The IFF-OBA team carried out a project field assessment from 13.02.2023 to 15.02.2023. The ob-jective of this new project is to install 6,000 smart prepaid water meters in Tanga town and ultimately to improve collection efficiency, recover outstanding arrears, reconnect disconnected customers, automatize meter reading/billing and reduce commercial losses. Tanga WSSA is currently piloting this technology (469 smart prepaid water meters installed).
The IFF-OBA team carried out a project field assessment from 01.02.2023 to 03.02.2023. The objective of this new project is to increase the water network in Mlangarini ward and connect 1200 new customers.
The IFF-OBA team carried out a project field assessment from 05.12.2022 to 07.12.2022. The ob-jective of this new project is to improve and extend water supply services at Kingolwira in Morogoro Municipal area in order to meet the increasing water supply demands as well as ensure sustainable water supply services.
The IFF-OBA team carried out a project field assessment from 28.11.2022 to 30.11.2022. The ob-jective of this new project is to increase the quantity of water injected in the existing network in the wards of Bomambozi, Mabogini and Passua wards by creating new intake points from Karanga river and to connect 500 new customers.
The IFF OBA team, in cooperation with the representatives from Ministry of Water (MoW) and the Ministry of Finance and Planning (MOFP), carried out a project verification visit to the Iringa WSSA from 21.11.2022 to 24.11.2022.
The IFF OBA team, in cooperation with the representatives from Ministry of Water (MoW) and the Ministry of Finance and Planning (MOFP), carried out a project verification visit to the Moshi WSSA from 14.11.2022 to 17.11.2022.
The IFF-OBA team carried out a project field assessment from 28th to 29th September 2022. The team visited the existing fault and aged water meters in the Miembeni, Bunkango and Kagondo areas. Team also visited existing tank at Kagondo and some of the dilapidated pipelines