MOSHI WATER SUPPLY AND SANITATION AUTHORITY-INTERIM VISIT

16. Jun 2022

The IFF Consultant conducted an interim visit from 15th – 17th June 2022. The aim of the visit was to assess the documentation of financial expenditure, to clarify some inconsistencies that occurred in the interim report. The team visited the rehabilitated storage tanks, domestic points, constructed 1.5km pipeline and interviewed newly connected customers. The total of 1,840 new customers have been connected. About 23,408 people will benefit from this project.

KAHAMA WATER SUPPLY AND SANITATION AUTHORITY-VERIFICATION VISIT

09. Jun 2022

The IFF OBA team, in cooperation with the representatives from Ministry of Water (MoW) and the Ministry of Finance and Planning (MOFP), carried out a project verification visit to the Kahama WSSA from 05.06.2022 to 08.06.2022. The visit was aimed at the verification of output targets

SINGIDA WATER SUPPLY AND SANITATION AUTHORITY-VERIFICATION VISIT

29. May 2022

The IFF OBA team, in cooperation with the representatives from Ministry of Water (MoW) and the Ministry of Finance and Planning (MOFP), carried out a project verification visit to the Singida WSSA from 23.05.2022 to 25.05.2022

SHINYANGA WATER SUPPLY AND SANITATION AUTHORITY-ASSESSMENT VISIT

09. Apr 2022

From 9th to 10th of April 2022, the IFF-OBA team carried out a project proposal field assessment at the Shinyanga Water Supply and Sanitation Authority (Shinyanga WSSA). The utility submitted a project proposal to the IFF Secretariat that included the procurement of cesspit exhauster truck and extension of waste stabilization ponds

MBEYA WATER SUPPLY AND SANITATION AUTHORITY-ASSESSMENT VISIT

08. Apr 2022

The IFF-OBA team carried out a project field assessment from 05th to 07th April 2022. The team visited the existing Iwambi treatment plant, the proposed site for the construction of storage tank and Kadete river.

TANGA WSSA-INTERIM VISIT

28. Feb 2022

The IFF OBA Consultant conducted an Interim visit from 22nd – 23rd February 2022. The aim of the visit was to assess the documentation of financial expenditure, to clarify some inconsistencies. The team visited the ongoing construction works of raising main, clear water tank and clarifier at the Mowe treatment plant. The project is intended to increase the production capacity of 1000m3/day.

KAHAMA WSSA-INTERIM VISIT

15. Feb 2022

The IFF Consultant conducted an Interim visit from 09th – 11th February 2022. The aim of the visit was to assess the documentation of financial expenditure and to clarify some inconsistencies. The team inspected the two procured exhauster trucks and visited the Busoka wastewater treatment plant.

SINGIDA WSSA-MONITORING VISIT

02. Feb 2022

The IFF - OBA team carried out a project monitoring visit on the 26th January, 2022. The team visited the Namfuo/Liti (control room and the equipped borehole), Kititimo well field (boreholes, collector tank and booster station) and the 200m3 Somoku storage tank. The connection of customers was on progress during the visit, with approximately 140 new customers connected out of 250 as an output target. Approximately 3,000 people will benefit from this project. The team also had the opportunity to visit the Automated Water Kiosks (ATM) and two different Prepaid smart water meters.

MTWARA WSSA IFF-OBA PROJECT ASSESSMENT VISIT

13. Oct 2021

The IFF-OBA team carried out a project field assessment from 22nd to 24th September, 2021. The team visited the existing boreholes, storage tanks and booster station at Mtawanya, Mangamba treatment plant, Mbuo source (boreholes), Hiari storage tank and Mchuchu source where the water blending will take place. The team also visited Chiko/Lilungu disposal site.

SHINYANGA WSSA VERIFICATION VISIT

20. Sep 2021

The IFF OBA team, in cooperation with the representative from Ministry of Water (MoW) and the Ministry of Finance and Planning (MOFP), carried out a project verification visit to the Shinyanga WSSA from 13.09.2021 to 15.09.2021. The visit aimed at the verification of output targets which include (i) installation of 15km water supply distribution pipelines, (ii) connection of 500 Nr metered new customers and construction of 3Nr. water kiosks in different areas, (iii) replacement of at least 2,000 Nr. faulty water meters in the existing distribution area and (iv) a collection efficiency of at least 90% within the entire service area. To date, a total of 551Nr new customers have been connected, 3,192Nr faulty meters have been replaced and 6 Nr water kiosks were constructed and are now operational.

WORKSHOP MOROGORO- LOAN DISBURSEMENTS AND PROGRESS REPORTING

02. Jul 2021

On 24th and 25th of June 2021, the IFF-OBA team organised a workshop on Loan Disbursements and Progress Reporting at the Morogoro Hotel in Morogoro region. A total of 29 participants from 14 different WSSAs, representatives from commercial banks, Ministry of Finance and the Ministry of Water were amongst the audience. The objectives of the workshop were to (i) brief utilities on Proper accounting and documentation of expenditure and regular progress reporting in IFF Projects (ii) to brief the utilities on the bank perspective about disbursement schedules. (iii)introduction of loan calculator and calculation of annual interest in financial model.

Please refer to the photo gallery for more insights!