The IFF-OBA team carried out a project field assessment from 28.11.2022 to 30.11.2022. The ob-jective of this new project is to increase the quantity of water injected in the existing network in the wards of Bomambozi, Mabogini and Passua wards by creating new intake points from Karanga river and to connect 500 new customers.
The IFF OBA team, in cooperation with the representatives from Ministry of Water (MoW) and the Ministry of Finance and Planning (MOFP), carried out a project verification visit to the Iringa WSSA from 21.11.2022 to 24.11.2022.
The IFF OBA team, in cooperation with the representatives from Ministry of Water (MoW) and the Ministry of Finance and Planning (MOFP), carried out a project verification visit to the Moshi WSSA from 14.11.2022 to 17.11.2022.
The IFF-OBA team carried out a project field assessment from 28th to 29th September 2022. The team visited the existing fault and aged water meters in the Miembeni, Bunkango and Kagondo areas. Team also visited existing tank at Kagondo and some of the dilapidated pipelines
The IFF OBA team, in cooperation with the representatives from Ministry of Water (MoW) and the Ministry of Finance and Planning (MOFP), carried out a project verification visit to the Morogoro WSSA from 29.08.2022 to 01.09.2022.
The IFF - OBA team carried out a project monitoring visit on 18th August 2022. The team visited the ongoing construction works of 12.6km raising main DN600 diameter steel pipe and Pulsator Clarifier, rapid sand filter at Mowe treatment plant. During the visit the clear water storage tank was completed. The project is intended to increase the production capacity by 1,000m3/day through rehabilitation of water Treatment Plant and 12,000m3 through construction of new pulsator clarifier and two new rapid sand filters. The overall implementation including civil works and supply of material is at 67.5%.
The IFF Consultant conducted an interim visit from 15th – 17th June 2022. The aim of the visit was to assess the documentation of financial expenditure, to clarify some inconsistencies that occurred in the interim report. The team visited the rehabilitated storage tanks, domestic points, constructed 1.5km pipeline and interviewed newly connected customers. The total of 1,840 new customers have been connected. About 23,408 people will benefit from this project.
The IFF OBA team, in cooperation with the representatives from Ministry of Water (MoW) and the Ministry of Finance and Planning (MOFP), carried out a project verification visit to the Kahama WSSA from 05.06.2022 to 08.06.2022. The visit was aimed at the verification of output targets
The IFF OBA team, in cooperation with the representatives from Ministry of Water (MoW) and the Ministry of Finance and Planning (MOFP), carried out a project verification visit to the Singida WSSA from 23.05.2022 to 25.05.2022
From 9th to 10th of April 2022, the IFF-OBA team carried out a project proposal field assessment at the Shinyanga Water Supply and Sanitation Authority (Shinyanga WSSA). The utility submitted a project proposal to the IFF Secretariat that included the procurement of cesspit exhauster truck and extension of waste stabilization ponds
The IFF-OBA team carried out a project field assessment from 05th to 07th April 2022. The team visited the existing Iwambi treatment plant, the proposed site for the construction of storage tank and Kadete river.