MOSHI WATER SUPPLY AND SANITATION AUTHORITY-INTERIM VISIT

20. Dec 2023

The IFF Consultant conducted an interim visit from 14th – 15th November 2023. The aim of the visit was to assess the documentation of financial expenditure, to clarify some inconsistencies that occurred in the interim report. The team visited the constructed four (4) chamber intakes and one (1) collection chamber at Karanga river, installed pump with capacity 160m3/h at 26m Head and transformer, constructed control room and 2.3km transmission pipeline constructed.”

 

 

The interim project visit and the Consultants’ recommendations will assist the utility in streamlining the reporting and documentation of expenditure. This, in turn, will benefit the final project verification that is required for the approval of the grant disbursement.