The IFF-OBA team carried out a project field assessment from 28.11.2022 to 30.11.2022. The ob-jective of this new project is to increase the quantity of water injected in the existing network in the wards of Bomambozi, Mabogini and Passua wards by creating new intake points from Karanga river and to connect 500 new customers.

 

The team visited the proposed new intake, the existing intakes (karanga, kili tank, ghoa spring), the proposed injecting point, existing customers in the wards who do not have enough pressure at the tap for water to flow and households who are not yet connected to the network.