Tanga City Water Supply Improvement Project II
Tanga Water Supply and Sanitation Authority completed IFF Project “Tanga City Water Supply Improvement Project II” The project envisaged the rehabilitation and extension of the MOWE Water Treatment Plant so as to increase their production capacity by 12,000 m3/day and the construction of 12.4 km transmission main. As part of this project, Tanga WSSA targets to increase production capacity by at least 3,000m3/d to total average production of 32,850m3/d. The utility achieved the following output targets; as of July 2023;
• Completed Construction of 12.157 km pipeline and construction of the 1,000 m3 clear water reservoir
• The lamella plates and perforated pipes are replaced, 1Nr pulsator clarifier and 2Nr sand filters are constructed operational.
• Treatment capacity is increased by 3,000 m3/d to a total average production of 32,998.27 m3/d for five months.
• Collection efficiency of 92% for a period of eleven (11) months.
The financial figures of the Project are summarised in the below data sheet;